//Neighbours building? Check the plans now!

Neighbours building? Check the plans now!

When your neighbour starts building a new house, check the building plans immediately. If there is any problem with them – and particularly if the value of your property could be prejudiced – seek legal advice on how to put a stop to the construction work without delay.

In a recent High Court case concerning the construction of a 5-storey house in an area of Cape Town with a 3-storey limit (presumably a loss of sea view was the problem), the Court remarked that you “are required to check actively for building plans every time any building work commences on a neighbour’s property.” Delay may disentitle you not only from having the approval of the plans set aside, but also from stopping construction in the interim.

Having said that, if you are the owner who is building, think carefully about starting work if approval of your plans is in any way open to challenge – take advice on whether you should first get the written consent of all neighbours.

The case in question shows the danger of proceeding regardless. The plan approval followed the granting of departures from zoning regulations and relaxations of title deed restrictions and, although the neighbours only realised that there was a problem after a considerable amount of construction had already taken place (some R13.4m worth), the Court found that the neighbour had given plausible reasons for the delay in acting, and ordered a halt to all building work. Worse, a demolition order is threatened if the plan approval is set aside.

(From newsletter by Maurice Phillips – Wisenberg)

UWRA COMMENT:

Complaints from residents about building work in their area will be taken up with City Council by UWRA and this could lead to work being stopped and/or delayed.

It is always advisable to consult UWRA and the Aesthetics Committee before your start renovations or building work. We can advise you on how to go about it in line with the heritage criteria for Woodstock. And again: if the plans are referred to us by Council at a later stage, it could lead to significant delays.

So consult us right from the beginning.